What method of ground fault testing does Schneider Electric recommend for circuit breakers?

Product Line:
MCCB's with integral ground fault protection

Resolution:
Schneider Electric recommends primary injection testing to comply with the requirements of NEC 230.95(C) for ground fault testing upon installation. 
Secondary injection testing may be done at the option of the customer for scheduled maintenance after the installation has been tested and commissioned.